Dietz Elkhorn Road Closure at Ralph Fair: Fair Oaks Ranch Rebuild

October 29, 2026

The City scheduled Dietz Elkhorn to close fully between Chartwell Lane and Ralph Fair Road starting at 3:30 p.m. on Friday, October 23, after afternoon school pickup, with traffic on both Dietz Elkhorn and Chartwell Lane detoured to Saddle Song. The City of Fair Oaks Ranch expects the closure to last about two to three weeks. Counting from October 23, that puts a reopening somewhere between November 6 and November 13. The City has said it will post an update when the road reopens or if the schedule changes.

The City calls this closure "Step 2" of a full-depth rebuild of about 1.2 miles of Dietz Elkhorn Road (East), from Fair Oaks Parkway to Ralph Fair Road. That rebuild runs into 2027, moving west one section at a time. When it's done, the road will have the same two lanes it has today. What changes is the space on either side of them and the pipe underneath.

The south shoulder grows from a sliver to five feet

The City's July 29, 2026 open house presentation compares the road today with the road being built.

Dietz Elkhorn today Dietz Elkhorn after reconstruction
Total width 28 to 29 feet 32 feet
Travel lanes 11 feet each 11 feet each
North shoulder 5 feet, paved 5 feet, paved
South shoulder 1 to 2 feet, paved 5 feet, paved
Drainage Bar ditches and existing culverts Bar ditches largely kept, culverts replaced, regrading

The lanes stay 11 feet wide. All of the extra width goes to the south side, where the paved edge grows from a foot or two to five feet, matching the north side. Community Impact's July 2025 report on the project described the paved shoulders as space for pedestrians, bicycles and carts. The design doesn't include a separate sidewalk.

The City is doing all of this inside the existing roadway corridor. No right-of-way is being acquired. Most driveways and mailboxes stay where they are, and the work is limited to adjustments where they're needed. According to the open house deck, one concrete driveway section will be replaced, and two custom mailboxes will be replaced in kind, with temporary mailboxes in place during construction. Mail and package delivery are expected to continue as usual.

Under the north shoulder, a new water main

The project was bid together with a separate one, the Dietz Elkhorn Water Line Project, which lays a new 12-inch water main under the north shoulder. Doing both at once means the road gets torn up one time instead of twice.

The pairing also explains the price. Community Impact's 2025 coverage reported a roadway-only estimate of $4.9 million, funded through 2024 bonds. On July 2, 2026, City Council approved a combined road and water line contract with D&D Contractors, Inc. for $4,559,083.95, with a 5 percent contingency that caps total authorization at $4,787,038.15. The City's FY 2025–26 budget set aside $6,078,758 across the roadway and water line accounts. The developer of the Sovereign at Fair Oaks agreed to pay 25 percent of the water line replacement portion. Pape-Dawson Consulting Engineers is the engineering firm on the project.

Some prep work started before the road itself was touched. A June 26 City memo said Spectrum began relocating utilities for the first phase on June 8, and that the work was slowed by a possible conflict with a CPS Energy line. On September 2, the City closed the section of Dietz Elkhorn at City Hall for utility work ahead of the reconstruction, routing traffic through No Le Hace and Saddle Song.

Ralph Fair goes first, Fair Oaks Parkway goes last

Because the rebuild is a long one, the order of the work decides which households deal with it when. The open house presentation splits construction into three phases, starting at the east end:

  1. Phase 1: Preakness Lane to Ralph Fair Road
  2. Phase 2: Windermere Drive to Preakness Lane
  3. Phase 3: Fair Oaks Parkway to Windermere Drive

The current full closure, which the City describes as reconstruction of "the section of Dietz Elkhorn near Ralph Fair Road," is at the Phase 1 end of the corridor. The City's notices use "Steps" and the open house deck uses "Phases," and the City hasn't published a map showing how the two line up.

In July, the City estimated construction would run from late August 2026 to late August 2027. The City's ClearGov capital project tracker lists an overall project duration ending November 30, 2027, which may include more than the construction itself. The tracker's timeline shows construction at 26.5 percent complete.

What the phases look like after this closure

A full closure is the exception in this plan. The City's standard traffic plan for each phase works differently:

  • One eastbound lane stays open at all times while crews work the other lane.
  • Westbound traffic is detoured around the work zone.
  • Some intersections within a phase close when alternate routes exist.
  • Residents on Dietz Elkhorn and on dead-end streets keep access at all times.

So for most of the next year, a drive toward Ralph Fair Road will usually go straight through the work zone. The drive back west is the one more likely to involve a detour.

Trash day has its own instructions. Put carts out in their usual spots, and the contractor may move them for pickup and return them afterward. The City asks Dietz Elkhorn Road (East) residents to wait on scheduling bulk or brush pickup until their phase reopens to two-way traffic. If you're planning fall yard cleanup, check first whether your stretch of the road has reopened.

The Chartwell Lane corner is still being worked out

The busiest moment on this road is school drop-off and pickup, which is why the City timed the closure to start after afternoon pickup. The open house presentation shows a redesigned Chartwell Lane and Saddle Song intersection. It notes that City Council plans to consider more traffic control so vehicles can safely exit Chartwell Lane during drop-off and pickup hours.

A June 26 City Manager's memo listed the options on the table:

  • The two dedicated left-turn lanes included in the bid design
  • Keeping the current intersection configuration
  • A four-way stop with flashing beacon lights
  • Lowering the school-zone speed from 20 mph to 15 mph during school hours

These are options under consideration, not a final design. Since Saddle Song is the detour route for the current closure, the intersection is carrying more traffic than usual this fall while the long-term decision is pending.

Where updates appear first

The City posts closure changes through its News Flash page, and the Notify Me sign-up sends those posts by email. The City's Regroup system handles emergency notifications. For a project-level view, including documents like the traffic control plan, the ClearGov capital project tracker carries the schedule and completion percentage. Questions about the project go to Grant Watanabe, the City's director of public works, at (210) 596-7255.

If you own a home along Dietz Elkhorn and are thinking about when to list around this construction calendar, The Ross Group can help you plan photography, showings and timing around each phase as it opens and closes. Request Your Complimentary Luxury Home Valuation, and we'll walk through how the corridor's schedule fits your plans.